UNDER CONSTRUCTION

Week That Was

Week Ending 1st May 2020

Discover the week that was onsite at 9 Lambert Street, Kangaroo Point.


Drone

March 2020

To fully capture the scale and location of Monterey Kangaroo Point, drone footage is taken every 3 months.

Timelapse

June 2019 to January 2020

Catch up on Monterey's journey from the beginning of the project to the start of the new year! 

MONTHLY MILESTONES

MAY 2020


Community Notice:


Deliveries of Cross Laminated Timber (CLT) are still occurring. Please note that access along Lambert St may be limited on some days as the delivery is unloaded from the trucks. We apologise for any inconvenience. 


  • Levels 4 - 7 CLT floors, columns & walls
  • Perimeter Scaffold & Signage to Level 8
  • Levels 1 - 4 Aluminium Midnight Cladding

For more information on CLT, visit the TIMBER tab.

PROJECTED SCHEDULE

June 2020

  • Levels 8 - 10 CLT floors, columns & walls
  • Perimeter Scaffold to Roof Level
  • Level 1 Internals
  • Levels 5 - 8 Aluminium Midnight Cladding
  • Levels 1 - 4 Glass Balustrade

July 2020

  • Display Lot 302 available for Inspection
  • Roof & Pergola Installation
  • Levels 2 - 4 Internals
  • Levels 9 - 10 Aluminium Midnight Cladding
  • Levels 5 - 8 Glass Balustrade

August 2020

  • Levels 5 - 8 Internals
  • Levels 9 - 10 Glass Balustrade
  • Perforated Gold Screen Installation Commenced
  • Scaffold Stripping Commenced
  • Level 1 Heated Pool Installation

September 2020

  • Level 9 Internals
  • Dual Lift Installation
  • CCTV & Security Systems Installed

October 2020

  • Level 10 Internals
  • Rooftop Recreational Area Complete
  • Scaffold Down
  • Crane & Hoist Dismantle

November 2020

  • Defects cleaning
  • Construction Completion
  • Decant site

December 2020

  • Settlements and Move-ins Commenced
  • Grand Opening Celebration